Performance Qualification Protocol
HelixOps Quality Management System - GxP Validation Documentation
1. Introduction #
This Performance Qualification (PQ) protocol verifies that the HelixOps system performs as expected under real-world operating conditions. It validates that all functional requirements from FS-HELIX-001 are met.
PQ Purpose
PQ testing confirms that the system consistently performs according to its specifications under normal operating conditions with typical user scenarios.
2. Test Scope #
1 Functional Testing
- • GRC module operations
- • Privacy module operations
- • Audit trail verification
- • Data export functions
2 Workflow Testing
- • Approval workflows
- • Multi-stage processes
- • Task management
- • Escalation handling
3 Integration Testing
- • Cross-module data flow
- • API integrations
- • Authentication flow
- • External system interfaces
4 Performance Testing
- • Response time validation
- • Concurrent user testing
- • Large data set handling
- • Stress testing
3. Functional Tests #
These tests verify core system functionality against the functional specifications.
| Test ID | Test Name | Description | Traces To | Status |
|---|---|---|---|---|
| PQ-FUNC-001 | Risk Creation | Create risk with all required fields | FUNC-RISK-001 | Pending |
| PQ-FUNC-002 | Risk Score Calculation | Verify auto-calculated risk score | FUNC-RISK-002 | Pending |
| PQ-FUNC-003 | Risk Heat Map Display | Verify risks shown on heat map | FUNC-RISK-003 | Pending |
| PQ-FUNC-004 | Control Creation | Create control linked to risk | FUNC-CTRL-001 | Pending |
| PQ-FUNC-005 | DPIA Workflow | Execute complete DPIA workflow | BUS-REQ-201 | Pending |
| PQ-FUNC-006 | DSAR Processing | Process DSAR request end-to-end | BUS-REQ-220 | Pending |
| PQ-FUNC-007 | Audit Log Generation | Verify audit entries created | BUS-REQ-007 | Pending |
| PQ-FUNC-008 | Report Export | Export report to PDF/CSV | BUS-REQ-014 | Pending |
4. Workflow Tests #
These tests verify end-to-end workflow execution across multiple system components.
Submit risk for approval, approve, verify status change
Execute DPIA through all approval stages
Assign task, complete, verify Action Center update
Verify overdue task escalation
5. Integration Tests #
These tests verify data flow and integration between system modules.
Test Scenario: Risk-to-Control Linkage
Test Scenario: Cross-Module Compliance
6. Performance Tests #
These tests verify system performance meets the specifications under various load conditions.
| Test ID | Test Name | Target | Actual | Status |
|---|---|---|---|---|
| PQ-PERF-001 | Page Load Time | <2 seconds (P95) | — | Pending |
| PQ-PERF-002 | API Response Time | <500ms (P95) | — | Pending |
| PQ-PERF-003 | Concurrent User Load | 100 users without degradation | — | Pending |
| PQ-PERF-004 | Large Data Set Query | 50,000 records <3 seconds | — | Pending |
7. Test Summary #
Execution Summary
Release Criteria
- [ ] All critical tests passed
- [ ] No unresolved critical deviations
- [ ] Performance targets met
- [ ] Test summary approved by QA
- [ ] Release authorization signed
Test Protocol Approval
Electronic signatures are considered equivalent to handwritten signatures in accordance with 21 CFR Part 11 requirements.